Part 6 of 9

Financial Model Phasing

CapEx per MW, OpEx breakdown, ARR trajectory, EBITDA, and IRR/payback.

Stabilized YoC

11%

Cap Rate

6.5%

Financial Projections

Revenue, OpEx, and NOI ($M)

Development Phase Progression

Revenue & Returns by Phase (100 MW Total)

Full CapEx Breakdown

100 MW Build-out ($M) - All Three Phases

Total: $1.3B ($13MM/MW)

CapEx Breakdown

Capital Expenditure Distribution

Strategic Interlock & Cash Flow Draw Schedule

MonthGrid CapEx ($M)DC CapEx ($M)Narrative
M-0120.0 (57%)2.0Interlock – wire CIAC to CPS Energy.
M-032.010.0Design – engineering & deposits.
M-061.030.0Civil – grading, substation pad, conduit.
M-122.080.0Shell – steel erection, roof, floors.
M-185.0100.0MEP – chillers, switchgear, generators.
M-225.020.0Energize – substation commissioning.
M-24018.0Live – final retainage, tenant move‑in.

Target Metrics

Target Stabilized Yield on Cost (YoC): 11-13%. Target Annual Recurring Revenue (ARR): $2.54MM per MW ($212/kW × 12 months). Target Stabilized EBITDA Margin: 56%. Market Cap Rate for stabilized Tier III assets: 6.5%.

Phased Deployment Model

The model uses a 100 MW phased deployment: Phase 1 (20 MW, 22 mo operational), Phase 2 (30 MW, 30-36 mo), Phase 3 (50 MW, 48-60 mo). Total project CapEx: ~$1.3B at $13MM per MW.

CapEx Per MW

Target CapEx for AI-Ready (Liquid Cooled) facilities: $13MM per MW. Phase 1 is front-loaded with substation and campus infrastructure costs. Phase 2 and Phase 3 benefit from existing infrastructure, reducing incremental CapEx.

CapEx Breakdown (100 MW)

Land & Civil: $20MM. Substation (138kV): $30MM. Core & Shell: $200MM. MEP Infrastructure: $850MM ($8.5MM/MW). Soft Costs: $100MM. Development Fee: $40MM. Contingency (5%): $60MM. Total 100 MW: ~$1.3B.

Phase 1: 20 MW

Build-out cost: $260MM ($13MM/MW, capital intensive with front-loaded substation). Annual Revenue (ARR): $50.9MM ($212/kW × 20,000 kW × 12). Net Operating Income: $28.5MM (56% margin). Yield on Cost: 11.0%.

Phase 2: 30 MW

Additional build-out cost: $390MM ($13MM/MW). Cumulative ARR (50 MW): $127.2MM. Cumulative NOI: $71.2MM. Blended YoC: 11.0%.

Phase 3: 50 MW

Additional build-out cost: $650MM ($13MM/MW). Total ARR (100 MW stabilized): $254.4MM. Total NOI: $142.5MM. Total CapEx: $1.3B. Blended YoC: 11.0%. Market demand represents 3x planned capacity (300+ MW opportunity).

Capital Stack (Phase 1)

Senior Construction Loan: $169MM (65% LTC at 7.5% interest). Sponsor Equity ("The Ask"): $91MM (35% LTC). Seed Raise (immediate): $10-15M for land rights and long-lead equipment deposits. Closing Raise: $76-81M at financial close.

Debt Service & DSCR

Phase 1 Annual Debt Service: ~$12.7MM (interest only at 7.5%). NOI: $28.5MM. Debt Service Coverage Ratio (DSCR): 2.24x. Lenders require minimum 1.25x DSCR; this provides significant cushion for financing.

Valuation & Refinance Strategy

Phase 1 Stabilized Valuation: $438MM (NOI $28.5MM / 6.5% Cap Rate). Value Creation: $178MM ($438MM - $260MM cost). Refinance Proceeds: ~$116MM (new loan at 65% of value minus payoff of $169MM). This "Refinance Roll" funds significant portion of Phase 2 equity requirement.