Development Timeline

Strategic Execution Plan

From land acquisition to revenue generation, our phased approach ensures efficient deployment of AI-ready infrastructure.

Q1 2026

Land Acquisition & Zoning

60+ acres secured in unincorporated Bexar County with county development permit.

Planned Milestone
Q2 2026

Power Agreement (100MW)

Sign an interconnect agreement with CPS Energy for initial capacity.

Planned Milestone
Q2 2026

Water Rights Secured

Finalize SAWS recycled water contract for 100% cooling needs.

Planned Milestone
Q3 2026

Phase 1 Construction Start

Groundbreaking for first 20MW data hall and substation.

Planned Milestone
Q4 2027

Phase 1 Commissioning

Ready for service (RFS) for anchor tenant deployment.

Planned Milestone

Fast-Track Deployment Strategy

Our aggressive 22-month timeline from land acquisition to first revenue demonstrates the unique advantages of San Antonio's streamlined regulatory environment, abundant infrastructure, and commitment to economic development.

22
Months to RFS
20MW
Phase 1 Capacity
100MW
Total Capacity